Building the Future 2020

Construction Update for the Week of August 20, 2018

Top Activities This Week

• Area B Curtain wall frame install.Aerial Photograph of BSHS Construction Site
• Rock cast exterior in progress on area F2.
• Roofing at area E2 black box and scene shop started.
• Nichiha panel install on the D2 radius complete.
• Tile install in the restrooms area C first floor.
• Concrete slab at E2 west corridor and orchestra room.

Upcoming Activities

• Area E1 CMU walls to bearing.Aerial Photo of BSHS Construction Site
• Area D1 first floor ceiling grid complete.
• Ceiling grid in area C to start.
• Roof Joist and Deck install on F1 locker room area.
• Roofing to start on area A high roof.
• Glue-laminated beam install.
• Terrazzo flooring to start in area D2.

Trivia of the Week
At this time last year, the BSHS team was still installing site storm drainage and performing site grading activities.

Front Entrance of the New BSHSCourtyard of the New BSHSCafeteria of the New BSHSRendering of Gym Area at the new BSHSRendering of the courtyard at the new BSHSRendering of the media center at the new BSHS


This page is dedicated to providing updates on the construction of the new Boiling Springs High School and the relocation of the Boiling Springs High School 9th Grade Campus to the existing BSHS facility.  The project is set to be completed during the 2020-21 school year. 
You can click here for answers to FAQs about the project.


Building the Future 2020 Logo

Boiling Springs High School Logo

Thompson Turner Construction Logo


Jumper Carter Sease Architects Logo

Website by SchoolMessenger Presence. © 2018 West Corporation. All rights reserved.