Building the Future 2020

Construction Update for the Week of May 14, 2018

Top Activities This Week

• High roof in area D2 completeAerial of Boiling Springs HIgh Construction Site
• Area C upper level masonry walls to bearing.
• Area C roof joist and decking started.
• Continued MEP overhead rough in for Area C and B.
• Masonry walls in Area B upper level in progress.
• Mud slab in auxiliary gym poured.
• Sand spread on baseball/softball fields. Irrigation on fields complete. Fence posts installed.

Upcoming Activities

• Roofing on Area D1 to start.Aerial of Boiling Springs HIgh Construction Site
• Area C roof joist and decking progress.
• Continue MEP overhead rough in for Area C and B.
• Continue Area B masonry upper level to bearing.
• Brick on Area D2 and D1 to continue.
• Baseball and Softball outfield sand to be mixed and sprig to be installed.

Trivia of the Week

The spray foam insulation being used on BSHS comes out of the spray gun with particles one tenth the size of spray paint and expands to two inches within 15 seconds.

Front Entrance of the New BSHSCourtyard of the New BSHSCafeteria of the New BSHSRendering of Gym Area at the new BSHSRendering of the courtyard at the new BSHSRendering of the media center at the new BSHS


This page is dedicated to providing updates on the construction of the new Boiling Springs High School and the relocation of the Boiling Springs High School 9th Grade Campus to the existing BSHS facility.  The project is set to be completed during the 2020-21 school year. 
You can click here for answers to FAQs about the project.


Building the Future 2020 Logo

Boiling Springs High School Logo

Thompson Turner Construction Logo


Jumper Carter Sease Architects Logo

Website by SchoolMessenger Presence. © 2018 West Corporation. All rights reserved.