Construction Update for the Week of October 29, 2018

Top Activities This Week

• Area E2 eyebrow framing complete.Aerial Photo of BSHS Construction Site
• Slab prep complete for D2 chiller yard and loading dock.
• Metal stud walls in area A complete.
• Terrazzo flooring through the main corridor on the classroom side.
• Brick at the press box complete.
• Fireproofing structure in locker rooms upper level.

Upcoming Activities

• Closing in on completion of exterior skin and dry in activities.Aerial Photo of BSHS Construction Site
• Baseball and Softball press box truss install.
• MEP overhead rough in on locker rooms upper level.
• Curtain wall frame install in area E.
• TPO roofing completion.

Trivia of the Week
There is roughly 12,000 square feet of metal stud wall framed in the administration wing to date.

Front Entrance of the New BSHSCourtyard of the New BSHSCafeteria of the New BSHSRendering of Gym Area at the new BSHSRendering of the courtyard at the new BSHSRendering of the media center at the new BSHS


This page is dedicated to providing updates on the construction of the new Boiling Springs High School and the relocation of the Boiling Springs High School 9th Grade Campus to the existing BSHS facility.  The project is set to be completed during the 2020-21 school year. 
You can click here for answers to FAQs about the project.


Building the Future 2020 Logo

Boiling Springs High School Logo

Thompson Turner Construction Logo


Jumper Carter Sease Architects Logo

Website by SchoolMessenger Presence. © 2018 West Corporation. All rights reserved.