Building the Future 2020

Construction Update for the Week of January 7, 2018

Top Activities This Week

• Press box windows installedBoiling Springs High School Construction Site
• Auditorium overhead rough in and metal stud framing in progress.
• Media center ceiling grid started.
• Elevator 2 install in progress.
• Hanging sheetrock in the auditorium.
• Overhead rough in for F1 & F2 upper level.
• Painting in lower level F1 & F2.
• Site concrete around Press box.

Upcoming Activities

• Flooring to continue through B wing.Aerial Photograph of BSHS Construction Site
• Casework install in classroom wings.
• Ceramic tile install in locker rooms.
• Press box casework, roll up doors, painting.
• Overhead rough in progress in E1 and E2.
• OSF Overhead inspection for the remainder of the classroom wings and A wing west.

Trivia of the Week
Rigging multiple pieces of steel with a crane in a single pick is called “Christmas Tree-ing”. See picture under upcoming activities!

Front Entrance of the New BSHSCourtyard of the New BSHSCafeteria of the New BSHSRendering of Gym Area at the new BSHSRendering of the courtyard at the new BSHSRendering of the media center at the new BSHS


This page is dedicated to providing updates on the construction of the new Boiling Springs High School and the relocation of the Boiling Springs High School 9th Grade Campus to the existing BSHS facility.  The project is set to be completed during the 2020-21 school year. 
You can click here for answers to FAQs about the project.


Building the Future 2020 Logo

Boiling Springs High School Logo

Thompson Turner Construction Logo


Jumper Carter Sease Architects Logo

Website by SchoolMessenger Presence. © 2019 West Corporation. All rights reserved.