Construction Update for the Week of February 25, 2019

Top Activities This Week

• Ceramic tile install in the lower level locker rooms. Boiling Springs High School Construction Site
• Terrazzo flooring in lower level F.
• Hanging and finishing sheetrock in timber areas.
• Insulating in F2 mechanical room.
• Kitchen equipment installation.
• Outdoor classroom forming.
• Press box and ball fields completion and final clean up.

Upcoming Activities

• Grinding and polishing terrazzo flooring in F and A wings. Boiling Springs High School Construction Site
• Ceiling grid install in upper level F.
• In-wall rough in for area A east side.
• Completion of kitchen equipment install.
• Interior glass install at classroom door side lights.
• Spring Athletics grand opening.


Front Entrance of the New BSHSCourtyard of the New BSHSCafeteria of the New BSHSRendering of Gym Area at the new BSHSRendering of the courtyard at the new BSHSRendering of the media center at the new BSHS


This page is dedicated to providing updates on the construction of the new Boiling Springs High School and the relocation of the Boiling Springs High School 9th Grade Campus to the existing BSHS facility.  The project is set to be completed during the 2020-21 school year. 
You can click here for answers to FAQs about the project.


Building the Future 2020 Logo

Boiling Springs High School Logo

Thompson Turner Construction Logo


Jumper Carter Sease Architects Logo

Website by SchoolMessenger Presence. © 2019 West Corporation. All rights reserved.